Object: Raw materials elevator of the oil extraction plant with a refinery capacity of: sunflower - 2000 tons/24 hours, rapeseed - 1500 tons/24 hours, soybeans - 1200 tons/24 hours (2nd stage)
Location: Vizirka village council, Kominternovskiy district, Odessa region, 2 km of the road to Yuzhniy Commercial Seaport, 1
Works Description: General construction works - arrangement of pile footing, foundations; metal structures producing and mounting (600 tons); metal structures profiled sheeting; metal-plastic windows and doors mounting; Three-floored brick building construction of electrical substation, distribution center and central control facility. Elevator production equipment mounting - silos ø32 m, with a capacity of 21,852.16 m3 of sunflower seeds (MUYANG), operative hoppers for dry and wet grains, grain dryer LAW SBC 226L (CFCAI), grain cleaning machines Bühler Schmidt-Seeger, Marot, chain flight conveyors MUYANG, band elevators MUYANG, truck tippers (Elevatorpromservice LLC, Nikolaev),distribution equipment, grain sampler. Principal contractor (without subcontracting).
Kinds of works: 2nd stage of construction:
- arrangement of pile footing
- arrangement of foundations
- metal structures producing and mounting together with profiled sheeting
- metal-plastic windows mounting
- hard surface arrangement of 9,575 sq. m area on the elevator territory
Beginning of construction works: June 2014
Project Owner: Allseeds Black Sea LLC
End of construction: May 2015